Project Summary
United supported the Columbia Energy Center with the design coordination, procurement, fabrication, and field replacement of a main steam/control stop valve during a scheduled outage. The scope included piping and structural modifications to the existing main steam system, procurement of critical materials, in-house fabrication, and coordinated field installation in an operating power generation environment.
Key Differentiators
- Engineering coordination for piping and structural modifications
- Procurement of forged wye block, P91 piping, and structural steel
- In-house fabrication of piping components
- Main steam/control stop valve replacement
- P91 piping installation
- Structural modification support
- Field installation during scheduled outage
- Coordination with plant personnel, subcontractors, and inspection teams
Technical Capabilities
- P91 and high-alloy piping
- Specialty welding
- Field machining
- Structural modifications
- Engineered heavy rigging
- Piping fabrication
- Operating plant execution
- Outage planning and coordination
- Critical-path mechanical work
Project Impact
The project required precise coordination of engineering, procurement, fabrication, and field execution within a defined outage window. United completed the work with no lost-time incidents, no quality issues, and disciplined adherence to customer requirements, demonstrating the ability to safely execute high-consequence mechanical work in an operating power generation facility.